FG Awards Over 70 Road Projects in North Central – Official

3 Min Read

  The Federal Government had awarded more than 70 road projects from 2017 to date in the North Central region as part of measures to improve infrastructural development in the country.

 

Mr Aganabah Bola,  the Acting Director Highway for the North Central, Federal Ministry of Works, disclosed this to the News Agency of Nigeria (NAN) at Patigi, Patigi Local  Government Area of Kwara.

He fielded questions on Saturday on the sideline of an inspection visit to some ongoing federal road projects in the state.

Bola said all the contractors handling the various roads projects in the region have returned to their respective sites to achieve remarkable progress before the raining season sets in.

He said the various ongoing road constructions had created employment opportunities and boost the economy of the areas where the work is in progress.

The acting director, who led the team on the inspection of ongoing federal government roads projects in Kwara, reaffirmed the determination of the federal government to further improve on the provision of infrastructure in all parts of the country.

He said the motive of the on-the-spot assessment of all ongoing road projects was to ensure that the roads are motorable before the raining season sets in.

The Federal Controller of Works in Kwara, Mr Wasiu Atitebi, said the federal government is not owing to any contractor handling any road project in the state.

The controller emphasised the need for all the contractors handling all ongoing federal roads projects to execute them in line with specifications.

The contractor handling 110km equalisation roads project of the Ilorin-Jebba highway in Kwara, Mr Wen Haiming, called on the federal government to release more funds to ensure early completion of the project in view of its economic importance.

Haiming said he only received N1 billion out of the N80 billion contract sum approved and awarded by the federal government in 2018.

The contractor attributed the slow pace of work on the road project to non-release of enough fund to acquire more hands and equipment for the speedy completion of the project.

“The roads being a major national road requires early completion but without adequate funding, the project might not meet 2021 slated for completion period,”  the contractor said.

Only over 10kms out of 110kms had so far been executed.

Other roads projects inspected were 5km llorin-Igbeti road at Ajasaip-Osun state boundary,  llorin-Egbe road and Offa bye-0pass.

Share this Article
Leave a comment

Leave a Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.