Lagos State Govt- Imota Rice Mill Set To Be Completed By June 2020

4 Min Read

The Lagos State Government on Monday said that its 32,000-metric-tonnes Imota rice mill would be completed in

June 2020.

Mr. Gbolahan Lawal, Lagos State Commissioner for Agriculture, made the disclosure during an inspection visit to

the rice mill at Imota, Ikorodu.

Lawal said the economic importance of the rice mill was very huge, considering the Federal Government policy on

importation of rice.

“The socio-economic importance of the mill is very significant to Lagos State.

“Considering the number of people that are consuming rice in the state, we realize the need for the quick completion of the mill.

“We are happy with the level of development and after the completion, I see jobs created.

“About 250,000 jobs will be created.

“The investment and the initiative of this administration are to ensure that this project is completed on time,’’ he said.

Lawal explained that the mill would create opportunities for the agriculture space, from bagging to transportation

and distribution.

“As a government, we have demonstrated that we have the capacity to complete this mill.

“The mill is expected to produce 2.4 million 50kg bags of rice and the cost benefits are very significant,’’ he said.

The commissioner commended Gov. Babajide Sanwo-Olu for sustaining the project with more investment, which

reflected the continuity of government.

Ms. Abisola Onasanya, Special Adviser to the Governor on Agriculture, said the team was at the site to monitor

progress made so far on the project.

According to Onasanya, the team will continue to meet with all contractors at the mill site fortnightly.

“We come here on a monthly basis to see what we have discussed in our meetings and to ensure that contractors are

actually keeping to the time,” Onasanya said.

She noted that there had been significant progress of work in the last four weeks.

One of the contractors, Henry Ossai, Managing Director, HenryKarl Construction Limited, pledged the commitment

of his company to deliver the project before the inauguration date.

Ossai said some equipment trapped at the seaport, slowed down the pace of work.

“But now, the equipment has started coming into site.

“We are working day and night to make sure we meet up with the target.

“Right now, there is no importation of rice, which means this mill is going to serve a lot of purposes, create jobs and

opportunity for the state.

“We want the mill to run; we want people to be employed and we are 100 percent committed to the completion at

the right time,’’ Ossai said.

READ: Bill Cosby Slams Eddie Murphy, Calls him “Hollywood Slave”

Mr. Sola Okeleye, General Project Manager, CIBA Construction Limited, said the rice to be produced in the mill

would be polished, single color and stone-free after going through all the stages of production.

Share this Article
Leave a comment

Leave a Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.