Electricity: GenCos fail to generate 3,347.5 Megawatts due to Gas Shortage

2 Min Read

Electricity Generation Companies (GenCos), comprising gas-fired and hydro stations said that they could not generate 3,347.5 megawatts of electricity on Wednesday due to unavailability of gas.

SEE ALSO: “You should be ashamed of yourself” Aisha Yesufu Insists Amaechi was Attacked despite his denial

This information was made known  in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained by News Agency of Nigeria (NAN) in Abuja on Thursday  .

The report also noted that 220 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.

Similarly, it said that 400.4 megawatts was not generated due to high frequency resulting from unavailability of distribution infrastructure.

The report, however, said that the GenCos released an average of 4,140 MegaWatts/Hour of electricity into the national grid on Wednesday .

It said that the electricity sent out by the GenCos was down by 95.89.13 megawatts from the 4,286 released on Tuesday.

The report revealed that the power sector lost an estimated N1.9 billion on Wednesday due to insufficient gas supply, distribution and transmission infrastructure.

On sector reform and activities, it said that the dominant constraint for Wednesday  was unavailability of Gas.

The report said that the peak generation attained on  was 4,502.5 megawatts.

Share this Article
Leave a comment

Leave a Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.